Road improvements and resurfacing: A547 Abergele Road, Llanddulas

Resurfacing
Work starts: Tuesday 24 November 2026
Work finishes: Friday 04 December 2026
What is happening?
Conwy County Borough Council will be carrying out carriageway resurfacing works on a 1.2km section of the A547 Abergele Road, commencing at Llanddulas Roundabout and extending westbound towards Old Colwyn.
To minimise disruption, the works will be undertaken in two phases:
- Westbound carriageway: Night-time working between 7:00pm and 5:00am from Tuesday 24 November to Saturday 28 November 2026.
- Eastbound carriageway: Daytime working between 7:30am and 5:30pm from Monday 30 November to Friday 4 December 2026.
To complete the works safely and efficiently, sections of the road will need to be closed periodically. A traffic management system, including convoy working, will be in place throughout the duration of the scheme.
Will it affect parking?
Yes - there will be no parking on affected sections while we do this work.
We will maintain pedestrian access at all times.
What is resurfacing?
Step 1 - remove the existing surface (this is called planing)
Step 2 – adjust or replace the ironwork, manholes & drainage gullies
Step 3 - clean the surface with a mechanical sweeper
Step 4 - lay a bond coating, to make sure the new surface sticks
Step 5 - lay the new surface
Step 6 - compact and level the new surface with rollers
Step 7 - repaint the road markings
Resurfacing is a noisy and dusty process, and we are sorry for the inconvenience this might cause. The new road surface will provide a smoother, quieter ride and will be a
long lasting benefit to the community.
Questions?
If you need more information, please contact the Environment, Roads & Facilities Advice Team on erf@conwy.gov.uk or call 01492 575337.
Thank you for your patience while our contractor carries out this work.
Posted on 23/11/2026